To stake out to the design elevation

To measure your position relative to an elevation in an RTK or conventional survey:

  1. Tap and select Stakeout / Elevation.
  2. Enter the Design elevation.
  3. Enter the As-staked name and Code.
  4. Enter a value in the Antenna height or Target height field and make sure that the Measured to field is set correctly.
  5. Tap Start.

    The coordinates of the current position and the distance above (cut) or below (fill) the design elevation are shown.

    Unless you are using a conventional instrument that supports tracking, the values appear only after you have taken a distance measurement.

  6. When the point is within tolerance, tap Measure to measure the point.

  7. Tap Accept to store the point.
  8. If you selected the View before storage option, the staked deltas you selected in the Stakeout options screen are shown. Tap Store.